Retarget a release
Change the release readiness target to reschedule the release period.
Antes de Iniciar
Role required: sn_dpr_model.product_manager or sn_dpr_model.release_admin
Procedimento
Resultado
- The readiness target date of the release is updated to the new date.
- For timeline-oriented releases, the key dates impacted are adjusted based on the retargeted date. This adjustment is made after recalculating the number of days that have changed from the original schedule.Nota:If a holiday schedule is attached to the release and the revised key dates fall on a holiday, the last workday before the holiday is considered as the revised key date.
O que Fazer Depois
Update the planned dates on the associated change requests manually because they are not automatically updated when you retarget the release.