Complete a problem task

  • Versão de lançamento: Australia
  • Atualizado 12 de mar. de 2026
  • 1 min. de leitura
  • Resolve and complete the problem task.

    Antes de Iniciar

    Role required: admin, problem_admin, problem_coordinator, problem_manager, or problem_task_analyst

    Procedimento

    Select Complete.
    work in progress state
    The problem task enters the Closed state with Close code as Complete.
    Nota:
    You can configure the Problem properties to reanalyze a task even after it is closed by selecting Re-assess. The state of the task changes from Closed to Assess. After all the problem tasks are completed or canceled, a notification is sent to the problem coordinator regarding the same.