Generate labor costs

  • Versão de lançamento: Australia
  • Atualizado 12 de mar. de 2026
  • 1 min. de leitura
  • Generate labor costs for projects and sub-projects based on the attribute-based resource assignments and the financial attributes configured in the planning attributes page.

    Antes de Iniciar

    Role required: sn_align_ws.spw_financial_user

    Por Que e Quando Desempenhar Esta Tarefa

    When the distribution of effort for a resource assignment is adjusted without changing the total planned effort, the system automatically recalculates and generates labor costs to align with the updated effort distribution. For example, consider a resource assignment of 100 hours distributed as 60 hours in January and 40 hours in February; now if you swap the efforts to make 40 hours in January and 60 hours in February. Now the system automatically adjusts the labor costs so that January reflects the cost of 40 hours and February reflects the cost of 60 hours, ensuring that costs accurately correspond to the revised effort distribution.

    Procedimento

    1. Navigate to Workspaces > Strategic Planning Workspace and select portfolio plan.
    2. Select a planning item from the Planning module.
    3. Select the Financials tab.
    4. Select Generate labor costs (Generate labor costs button.).
    5. Select Generate on the Generate labor costs confirmation window.
      Nota:
      Alternatively, you can activate a scheduled job to generate labor costs at the required cadence. For more information, see Activate scheduled job to generate labor costs for your planning items.