# Realign resource assignment to project task

# Realign resource assignment to project task {#ariaid-title1}

* Versão de lançamento: Australia
* 
* Atualizado 12 de mar. de 2026
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 1 min. de leitura

Realign or synchronize the resource assignment dates with the project task dates. This synchronization helps to schedule and align the resource assignments with the timeline of project task.

## Antes de Iniciar

Role required: it_project_manager

## Procedimento

1. Navigate to AllWorkspacesProject Workspace and open a project.
2. From the project planning pane, double-click the Planned start date or Actual start date of a project task.
3. Edit the field and select Ok.
4. From the project task row, select the row context menu and then select Realign assignments to task.  
   Alternatively, use the Resources not synced icon ![]() to synchronize the resource assignments dates with the project dates at a project level. Realign assignments to task related link is available to perform the same action while using forms.

## Resultado

The resource assignments dates are synchronized with the project task dates.
**Conceitos relacionados**   

* [Resource assignments in Project Workspace](https://servicenow-prod.fluidtopics.net/u1IdgT2TNvuQ29e47e5YIg "Optimize project execution by assigning resources to tasks within the Project Workspace. You can create resource assignments for any project or project task, specifying the tasks to be performed and the resources to be allocated.")
* [Project Workspace reference](https://servicenow-prod.fluidtopics.net/io~~d1EBtRjOaoVBCzD0BQ "Reference information to provide additional details about Project Workspace, such as the fields, user roles, tables, scheduled jobs, system properties, and custom scripts.")