Update the resource aggregates

  • Versão de lançamento: Australia
  • Atualizado 12 de mar. de 2026
  • 1 min. de leitura
  • From the Resource Manager view, you can update the resource aggregates for a specific time frame.

    Antes de Iniciar

    Role required: pps_admin

    Por Que e Quando Desempenhar Esta Tarefa

    You can use the Update Resource Aggregates related link in the following scenarios:
    • If you notice a discrepancy in aggregates and want to generate correct data.
    • If you want to synchronize aggregates with the Resource Allocation Daily [resource_allocation_daily] entries for a specific time frame.

    Procedimento

    1. Navigate to All > Resource Management > Resources > Users.
    2. Select a User ID.
    3. Select the Update Resource Aggregates related link.
    4. In the window, provide a start date and end date.
    5. Select OK.