# Create a demand task

# Create a demand task {#ariaid-title1}

* Versão de lançamento: Australia
* 
* Atualizado 12 de mar. de 2026
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 3 min. de leitura

Create tasks for a demand to delegate cost, effort, risk, and benefit assessment
activities. Assign a resource or group to the demand task to track the actual time and
effort spent on performing the specified activities.

## Antes de Iniciar

Role required: it_demand_manager

## Por Que e Quando Desempenhar Esta Tarefa

You create demand tasks to plan the work for demands rather than for the target work
entity such as a project, change, defect, or enhancement. For more information, see
[Demand tasks](https://servicenow-prod.fluidtopics.net/2Ta2hVRkY27PuCXWg3PDag "A demand task is a unit of work, created within a demand, to break down initial planning activities before converting the demand into a project, change, enhancement, or defect.").

* Planned dates, actual dates, and original dates are part of project tasks not demand tasks.
* The due date indicates the date on which the task is targeted for completion and doesn't affect the demand workflow. Project tasks, however, affect the project completion dates if the planned dates and actual dates are changed.
* Don't support the creation of nested demand tasks.
* Don't support task constraints such as the settings Start ASAP and Start on a specific date.
* Don't support an execution type such as Agile, Waterfall, or Hybrid.
* You assign resources for a demand task use the Assigned to field, Additional Assignee list, and Assignment Group fields.

{#create-demand-task__ul_ejt_ccf_2hb}

Resources assigned to a demand task can submit the time spent on it using a time
card.

If you're creating a demand task with the PPM Standard Multicurrency (com.snc.ppm_multicurrency) plugin activated and Demand Currency view enabled, additional fields become available in addition to the Default view. For more
information about the fields that are available only in the Demand Currency view, see [Multicurrency in Demand Management](https://servicenow-prod.fluidtopics.net/jYc9IrOcIdv~~XnZqi~rQA "Manage and track the financials of your demands in the corporate currency, regional currency, or the same currency that you want to use for managing the project using the multicurrency feature. The corporate policy typically governs the choice of this preference.") and [Multicurrency fields in demand-related forms](https://servicenow-prod.fluidtopics.net/Pd0axRV004dz~BZT4vrikA "When you enable the Demand Currency view in a Demand, Cost Plan, and Cost Plan Breakdown forms, you can observe the multicurrency fields in the Financials section of the forms.").

## Procedimento

1. Navigate to AllDemandDemandsAll.
2. Select the demand to which you want to add tasks.
3. Add or edit a demand task from the Demand Tasks related list:  
   * To add a demand task, select New.
   * To update the details of an existing demand task, select the record and then select Edit.
   {#create-demand-task__ul_h4d_yb3_mhc}
4. On the Demand Task form, fill in the fields.  
   For a description of the field names, see [Demand task form](https://servicenow-prod.fluidtopics.net/u65U~bbSHTwXw1sqhJP67g "Use the demand task form to create tasks for a demand.").
5. Select Save.  
   After completing your work on the demand task, select Update to return to the demand page.

## O que Fazer Depois

Create resource assignments and add cost plans, benefit plans, and risks to the demand depending on your role. Use the following related links to access these tasks.{#create-demand-task__table_fn3_13f_2hb__entry__2}

| Related Links | Description |
|:-|:-|
| Add Cost Plan to Demand | Add a cost plan to capture the costs of demands. Create a cost plan to specify the unit cost of a cost type for a fiscal period. This link appears if the Category value is set to Cost estimate and the user has the `it_project_manager` or `it_demand_manager` role. Select the link to open the cost plan form and fill in the details. For more information, see [create a cost plan](https://servicenow-prod.fluidtopics.net/VrQZaER8BuJg~R0j61POfg "Create a cost plan to specify the unit cost of a cost type for a fiscal period. Project cost plans capture the costs of projects."). |
| Add Resource Plan to Demand | Create a resource plan to find the availability of resources and add the resource plan to the demand. This link appears if the Category value is set to Effort estimate and the user has the `it_resource_user` role. Select the link to navigate to the Resource Plans page and request resources. For more information, see [Create and manage resource assignments for a demand](https://servicenow-prod.fluidtopics.net/qHF15d6UFJxyw698CjSgsA "As a resource requester, find the availability of the resources, and create and manage the resource assignments for a demand."). |
| Add Benefit Plan to Demand | Create a benefit plan to capture the potential benefits accrued by the demand when the demand is executed. This link appears if the Category value is set to Benefit estimate and the user has `it_project_manager` or `it_demand_manager` role. Select the link to open the benefit plan form and fill in the details. For more information, see [Create a monetary benefit plan for a demand](https://servicenow-prod.fluidtopics.net/MrmGgszCtQ9jMWU6SdtuKg "Demand benefit plans capture the potential benefits accrued by the demand when the demand is executed. Create a monetary benefit plan to specify the estimated benefit in a category for a fiscal period."). |
| Add Risk to Demand | Add risks that can potentially impact the success or outcome of the execution of the demand. This link appears if the Category value is set to Risk estimate and the user has `it_project_manager` or `it_demand_manager` role. Select the link to open the risk form and fill in the details. For more information see, [add a risk](https://servicenow-prod.fluidtopics.net/7ve1IyK5wvzj4040juI_cQ "The demand manager typically works with a business relationship manager to identify stakeholders and elicit requirements, risks, and other important information."). |
[Tabela 1. Demand Task form related links]