# Change the planned start date of a project

# Change the planned start date of a project {#ariaid-title1}

* Versão de lançamento: Australia
* 
* Atualizado 12 de mar. de 2026
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 3 min. de leitura

Adjust the schedule of a project by changing the planned start date of a project and
shifting it later or earlier than the current planned schedule.

## Antes de Iniciar

Role required: it_project_manager

## Por Que e Quando Desempenhar Esta Tarefa

Changing the planned start date of a project to a new date also moves all its tasks and subprojects relative to the updated start date of the project. You can change the planned start date of a project when the following conditions are true:

* The State of the project is Pending or Open.
* To move the start date of a project in WIP state, set the Enable move project for WIP projects property (com.snc.project.move_project.wip) to true. The default value of this property is false.
* No project_funding records are selected for execution.
* The project actual dates are not populated.

{#change-planned-start-date-of-project__ul_eyr_nxb_yfb}  
Nota:  
* The Move project option is available for a project only when it has a task or subproject.
* If an agile phase with sprints is associated to the project, then changing the planned start date of the project also clears the start and end dates of the sprints.
{#change-planned-start-date-of-project__ul_zkq_qck_pgb}

## Procedimento

1. Change the planned start date of a project using either of the following options.

   | Option | Steps |
   | From the Planning console | 1. Navigate to AllProjectProjectsProject Workspace. 2. Open the project for which you want to change the planned start date. 3. In the Planning Console, select the more actions icon (![More Actions icon]()) and then select the Move project option. {#change-planned-start-date-of-project__ol_vf4_cnk_wfb} |
   | From the Project form | 1. Navigate to AllProjectProjectsAll. 2. Open a project for which you want to change the planned start date. 3. On the Project form, select the Move project related link. {#change-planned-start-date-of-project__ol_ovd_mjj_wfb} |
   |-|-|

   {#change-planned-start-date-of-project__choicetable_bx2_kjj_wfb}
2. In the dialog box, pick a date.
3. Select or clear the Move all tasks regardless of constraint type check box.  
   * Clearing the check box moves the tasks with Start ASAP constraint only to the new project date.
   * Selecting the check box moves all the project tasks irrespective of their constraints to the new project date with the same offset except the task with Start ASAP constraint.

   {#change-planned-start-date-of-project__ul_hsc_lcx_npb}

   This check box is selected by default.  
   Nota:  
   The tasks in WIP and Close states are not moved.
4. Select OK.

## Resultado

* The planned start date of the project is updated to the new date.
* Program dates are updated relative to the project start date.
* If the Move all tasks regardless of constraint type check box is selected, all project tasks with Start on specific date and Start no earlier than constraints are moved to a new start date by the same offset as from the earlier project start date. The constraint date is also moved by the same offset.

  For example, say a project is starting on November 10 with a
  Start On task starting on November 15, giving an offset of five days. If you
  move the project start date to November 20, then the task start date will be
  moved to November 25, maintaining the five-day offset from the project start
  date.
* All project tasks with Start ASAP constraint are moved to the new start date based on the Constraint Date field on the project form. The tasks must be in the Open or Pending state.
* If the Change Resource Plan and Cost Plan Start Date with Demand or Project Start Date Change property is selected, all related entities like cost plan, resource plan, and benefit plans are moved relative to the project start date. For more information on how to set this property, see [Properties installed with Project Management](https://servicenow-prod.fluidtopics.net/5g2jgCRf8cbHrKVowB0QMA#r_InstalledWithProjectManagement__project_application_properties).
{#change-planned-start-date-of-project__ul_b5p_qbd_yfb}
* **[Pre-date a project task](https://servicenow-prod.fluidtopics.net/3h_wtdhcAA3FXpfi5hX_lw)**   
  Move the planned start date of a task prior to the planned start date of a project. Adding a pre-dated task allows you to accommodate tasks which need to start before the planned start date of a project.

**Conceitos relacionados**   

* [Create and manage waterfall projects](https://servicenow-prod.fluidtopics.net/T071mWYfzvRKjtxr_DwplA "Plan, create, and manage projects using the Waterfall methodology.")
* [Costing add-on in Project Management](https://servicenow-prod.fluidtopics.net/0qtv8eIoYDNBeoq2rXSxVg "The Project Management costing add-on connects the Project Management application to the Cost Management application to allow for estimating and tracking the costs associated with projects.")  
**Tarefas relacionadas**   

* [Create a project task from a project](https://servicenow-prod.fluidtopics.net/QW63Z_o1ZL9vFxnyQoGxOQ "Create tasks from the project form to break down project objectives into manageable units of work.")
* [Create a parent-child relationship on the Project Task form](https://servicenow-prod.fluidtopics.net/aisbbo47AfB~calO3uLPAw "Create a child task from any project task form.")
* [Create a monetary benefit plan for a project](https://servicenow-prod.fluidtopics.net/5kkfVfPdTlXWgufbMCMvfQ "Create a monetary benefit plan to specify the estimated benefit in a category spanning one or more fiscal periods. Project benefit plans capture the potential benefits accrued by the project when the project is executed.")
* [Create a non-monetary benefit plan for a project](https://servicenow-prod.fluidtopics.net/WKxXLvVlkTFlUb8OlL1PPg "Create a non-monetary benefit plan to specify the estimated benefit in a category spanning one or more fiscal periods. Project benefit plans capture the potential non-financial benefits accrued by the project when the project is executed.")
* [Associate monetary and non-monetary benefit plans](https://servicenow-prod.fluidtopics.net/vI2jptooAaEcnv0NgRbazw "Associate monetary and non-monetary benefit plans, so that you can capture the potential benefits (financial and non-financial) accrued by the project for the hybrid benefit plans.")
* [Create a project cost plan](https://servicenow-prod.fluidtopics.net/VrQZaER8BuJg~R0j61POfg "Create a cost plan to specify the unit cost of a cost type for a fiscal period. Project cost plans capture the costs of projects.")
* [Recalculating costs of all resource plans in a project](https://servicenow-prod.fluidtopics.net/OtyoYxyjtz~j6Ybw4PQqsg "Recalculate the resource costs of all resource plans in a project whenever the hourly rates change in the associated rate model so that the plan costs are up to date.")
* [Create an expense line](https://servicenow-prod.fluidtopics.net/mBNLS0_DAaJXMKgFKCGVaA "A project expense line is cost associated with a specific source, such as a user, fixed asset, or a CI. Expense lines are part of project cost plans.")
* [Update a project](https://servicenow-prod.fluidtopics.net/D7081Pka97TWEmWa5Y3~0g "Update the project and make adjustments in fields to handle scope, cost, and schedule. While a project is underway, keep actual values as current as possible. Continue to measure actual values, analyze the impact of any potential project risks.")
* [Copy a project](https://servicenow-prod.fluidtopics.net/eO6Pqmb2HhnVhaueXVDBWQ "Another option for creating a project is to copy an existing project with all its tasks and relationships. After you specify the start date for the copy, the system adjusts all task start and end dates automatically.")
* [Assign a project schedule](https://servicenow-prod.fluidtopics.net/z_shjXugjP8qzcNyD8_3Cw "Without an assigned schedule, a project calculates a day as a full 24 work hours. To schedule tasks by a more realistic work day, assign a schedule to the project. If the schedules provided in the base system do not suit your needs, define a new one.")
* [Create baseline of a project](https://servicenow-prod.fluidtopics.net/bq_bqgv0TKrzxvS5si499w "Create a schedule baseline and financial baseline of a project. A schedule baseline captures planned dates of all tasks and milestones at a particular moment in time. A financial baseline captures benefit and financial metric information (snapshot of cost plan, benefit plan, and project-level financial metrics) at a particular moment in time.")
* [Create a milestone](https://servicenow-prod.fluidtopics.net/_asVrP9WOIbzMauwCMg2dg "A milestone is a project task with a duration of zero (0). Use milestones to mark key dates in your project, such as key decision points, approvals, and holidays. Milestones are treated like any other project task and you can create dependencies between tasks and milestones.")
* [Activate project task email notifications](https://servicenow-prod.fluidtopics.net/PCQkkI1b8~bs_mgwqf8SHg "The following email notifications for the Project Management application are available by default, but are inactive. You must activate them manually.")
* [Create a cost type definition](https://servicenow-prod.fluidtopics.net/IFthHznC~1nEgj3CUBFKEQ "Create a cost type definition to associate a cost type, operating, or capital, to an account in the General Ledger from the Financial Management application. Create a cost type definition if you are using Project Portfolio Management with Financials.")
* [Generate labor costs](https://servicenow-prod.fluidtopics.net/GMv6JkWmU0eG5NB2WtVN8A "Generate labor costs based on the planning attributes configured for financials in the planning attributes page for the resource assignments in a project.")
* [Create a project status report](https://servicenow-prod.fluidtopics.net/XtwMdfldzALf5nKLAPiYpg "Create project status report from the related lists of the project form. The project status report created for the most recent status date updates the status of the project in portfolios.")
* [Allocate budget to a project](https://servicenow-prod.fluidtopics.net/FxrYPa0O79XSnX8KN2oKig "Set the budget of a project according to the fiscal years.")
* [Migrate budget of active projects to Next Experience](https://servicenow-prod.fluidtopics.net/NJPoKAMxLVCc~3QPrThULQ "Migrate the project budget to Next Experience to manage the financials using Project Workspace.")
* [Migrate financial baselines of projects to Next Experience](https://servicenow-prod.fluidtopics.net/UlAxBZJJBOFvDgVEtw9O_w "Migrate the financial baselines of your project to Next Experience to manage the financial using Project Workspace.")
* [Pre-date a project task](https://servicenow-prod.fluidtopics.net/3h_wtdhcAA3FXpfi5hX_lw "Move the planned start date of a task prior to the planned start date of a project. Adding a pre-dated task allows you to accommodate tasks which need to start before the planned start date of a project.")
* [Starting a project](https://servicenow-prod.fluidtopics.net/GQfBUAt~7~k9CuAreml7_g "Initiate a project by changing the project state to Work in Progress. Define important aspects of your Agile, Waterfall, or Hybrid project such as the duration, estimated cost, and net value to your organization to efficiently track the project's progress.")