Modify a project task dependency

  • Versão de lançamento: Australia
  • Atualizado 12 de mar. de 2026
  • 1 min. de leitura
  • Modify a dependency when editing the tasks that are linked in the dependency, the dependency type, or the lag time.

    Antes de Iniciar

    Role required: it_project_manager

    Por Que e Quando Desempenhar Esta Tarefa

    Project task dependencies are saved on the Planned Task Relationship [planned_task_rel_planned_task] table. You can access dependencies from the planning console.

    Procedimento

    1. Double-click a dependency on the Gantt chart of the planning console.
    2. On the form, fill in the details.

      For more information, see Planned Task Relationship form.

      Figura 1. Planned Task Relationship form
      Planned Task Relationship form
    3. Select Update.
      You can view dependencies in the Project Task related list on a Project or Project Task form and from the Project Tasks list on the workbench. These columns show the dependencies: