---
sourceDocument: Australia Strategic Portfolio Management
sourceDocumentLink: https://servicenow-prod.fluidtopics.net/r/pt-BR/it-business-management

 Release :

    - australia

ft:locale :

    - pt-BR

ft:publication_title :

    - Australia Strategic Portfolio Management

ft:clusterId :

    - itbm

bundleId :

    - itbm

workflow :

    - Technology


---

# Link change requests to a project task

# Link change requests to a project task {#ariaid-title1}

* Versão de lançamento: Australia
* 
* Atualizado 12 de mar. de 2026
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 1 min. de leitura

Link change requests to tasks on the Project Task form. You can link change requests
only to project tasks that have no child tasks.

## Antes de Iniciar

Role required: it_project_manager

## Por Que e Quando Desempenhar Esta Tarefa

You can link any change request record to a project task, regardless of the change request schedule or state. However, as a good practice, consider:

* Change Schedule: The change request has a schedule that falls within the time frame of the project it links to. Or, it has no values in the Planned start date and Planned end date fields in the Schedule section of the Change Request form.
* Change State: An Open or Pending state is required when linking a change request. Changes that are already in progress or closed can be stopped and copied to a new change request.
{#t_LinkChangesToAProjectTask__ul_i1y_2ny_dq}

## Procedimento

1. Open a project task that does not have any child tasks.  
   You can cannot link change request to the tasks that already have child tasks.
2. Select one of the following related links:
   * Link an Existing Change Request to Project Task:

     In the dialog box that appears, enter or select the change that you want to link.
   * Create Change and link from Project Task:

     The Change Request form appears. Enter the information in the form. The short description of the change request is taken from the project task.

   {#t_LinkChangesToAProjectTask__choices_dy5_jqk_zp}  
   Nota:  
   These related links are available only when the project task type is waterfall.

## Resultado

On the Project Task form, a notification appears at the top specifying that the task is linked to one or more change requests.Figura 1. Example for Task designated for linked change requests in the related list
**Conceitos relacionados**   

* [Change requests and project tasks](https://servicenow-prod.fluidtopics.net/kmAzQeOYDZKFhyjFFrusnQ "Large-scale changes approved by your change approval board (CAB) require new or existing projects to be implemented.")

