# Recalculate costs

# Recalculate costs of resource assignments of a demand {#ariaid-title1}

* Versão de lançamento: Australia
* 
* Atualizado 12 de mar. de 2026
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 1 min. de leitura

Recalculate the costs of all active resource assignments of a demand whenever the hourly rates change in the associated rate model so that the plan costs are up to date.

## Antes de Iniciar

Confirm the following setup:

* The demand must be active.
* The demand must have an active rate model assigned.
{#recalculate-resource-costs-of-a-demand__ul_m3y_jqy_mhb}Role required: demand_manager

## Por Que e Quando Desempenhar Esta Tarefa

This option recalculates the costs of all resource assignments of the demand at once. You can also open a resource assignment from the Resource assignments related list to [recalculate the resource costs of an individual resource assignment](https://servicenow-prod.fluidtopics.net/1N2WnKYH8qWcFSKfjHDo8Q "Recalculate the resource costs of an individual resource plan for a project or demand whenever the hourly rates change in the associated rate model.").

## Procedimento

1. Navigate to AllDemandDemandsAll.
2. Open a demand.
3. On the Demand form, right-click on the header bar and select the Recalculate Resource Costs.
4. In the Recalculate Resource Cost form, fill in the fields.  
   For a description of the field names, see [Recalculate resource costs form](https://servicenow-prod.fluidtopics.net/rWnMAG1CDFo2lhnday5~gA "Use the recalculate resource costs form to make sure that the resource assignment costs are up to date.").
5. Select OK.
{#recalculate-resource-costs-of-a-demand__steps_z2s_vxs_lhb}

## Resultado

* Recalculates the selected resource costs of all the applicable resource assignments in the demand based on the latest hourly rates. The hourly rates are derived from the rate model associated with the demand.
* Updates the recalculated resource costs on the respective cost fields on the resource assignment form and the Resource assignments related list.
* Reflects the revised values in the respective cost fields of the demand.