# Track project budget in project currency

# Track project budget in project currency {#ariaid-title1}

* Versão de lançamento: Australia
* 
* Atualizado 12 de mar. de 2026
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 1 min. de leitura

Allocate budget to a project and enter amounts for capital expense budget (Capex) and
operating expense (Opex) budget in project currency. The sum of the Capex and Opex budgets
are calculated as total budget in project currency.

## Antes de Iniciar

Role required: it_portfolio_manager

## Por Que e Quando Desempenhar Esta Tarefa

Allocate budget in a similar manner as you do with functional currency. For more
information, see [Allocate
budget to a project](https://servicenow-prod.fluidtopics.net/FxrYPa0O79XSnX8KN2oKig "Set the budget of a project according to the fiscal years.").

Enable the project currency view of the Project form to allocate budget in
project.

## Procedimento

1. Click the Project Budget related link of the Project form.  
   {#allocate-budget-project-currency__table_h2y_3lb_1kb__entry__2}

   | Field | Description |
   |-|-|
   | Currency | Currency in which budget is allocated for a project. If you activate multicurrency plugin, then you have the option to budget in project currency or functional currency. |
   | Capex Budget in Project Currency | Planned expense amount allocated for capital expenditure in the selected currency. |
   | Opex Budget in Project Currency | Operating expense amount in the selected currency. |
   | Total Budget in Project Currency | Sum of Capex and Opex amounts. The total project funding budget amount rolls up to the Budget cost in project currency field. |
   [Tabela 1. Project Budget form]

   {#allocate-budget-project-currency__table_h2y_3lb_1kb}
2. Click OK.
3. Click the Project Budget related list to update or view the record.

## O que Fazer Depois

The project target and budget expense values for both capital and operating expenses for a single fiscal period is stored in the [Project Funding \[project_funding\] table](jFb1lUglcr9comLJmrPRkQ#multicurrency-fields-project-form__project_funding_project_curr). When you update the project funding record, the amounts are converted to project currency.