Configure budget attribute at instance-level to allocate budget

  • Versão de lançamento: Australia
  • Atualizado 12 de mar. de 2026
  • 1 min. de leitura
  • Configure the budget attribute by expense type or cost type as an instance-level to work on budget allocations for your projects using Project Workspace.

    Antes de Iniciar

    Importante:
    Existing customers cannot change the budget attribute to cost_type.

    Procedimento

    1. Navigate to All > System Properties > Properties.
    2. Filter the Name column to locate and open sn_invst_pln.budget_allocation_attribute property.
    3. Update the Value field to one of the following.
      • cost_type - view financials by cost types such as Hardware Opex, External labor Capex, Software Capex, Software Opex, and so on.
      • expense_type - view financials by expense types such as Capex and Opex.
    4. Select Update.