Create a project task in the project workbench

  • Versão de lançamento: Australia
  • Atualizado 12 de mar. de 2026
  • 1 min. de leitura
  • Create a project task for a waterfall phase.

    Antes de Iniciar

    Role required: it_project_manager

    Por Que e Quando Desempenhar Esta Tarefa

    While creating a project task in the project workbench, the time constraint type is defaulted based on the project type.
    • For a manual project, the default constraint is Start On and cannot be changed.
    • For an automatic project, the default constraint is Start ASAP and can be changed to Start On if required.
    • When the constraint is Start ASAP, the Planned start date is disabled.
    • When you create an agile phase and associate a sprint, the start date of the task is set from the sprint start date and the constraint becomes Start On automatically.

    Procedimento

    1. Select a waterfall phase in the project workbench timeline.
    2. Select New in the detail view.
    3. Fill out the Project Task form.
    4. Select Submit.