Associate a time card with a resource plan
If one resource is allocated to identically named tasks in two resource plans, use the following procedure to specify the resource plan the time card should be allocated to.
Antes de Iniciar
Role required: resource_manager
Por Que e Quando Desempenhar Esta Tarefa
- A resource plan can be associated with a time card only if the resource plan contains hard allocations for the user.
- If a resource plan isn’t associated manually to a time card, then a resource plan is auto-associated. The auto-association is done based on the selected Task in the time card.