# Predecessor dependencies in the planning console

# Predecessor dependencies in the planning console {#ariaid-title1}

* Versão de lançamento: Australia
* 
* Atualizado 12 de mar. de 2026
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 1 min. de leitura

In the WBS section of the planning console, you can create dependencies between tasks
by specifying a series of values.
The Predecessor column on the planning console can specify dependencies between tasks. The values that you put in this column must be in the following format:

`{WBS_number}{dependency_type}+{lag_time}`  
Where

* `WBS_number` is the number of the predecessor task in the relationship.
* `dependency_type` is one of the [types of dependencies](https://servicenow-prod.fluidtopics.net/QLtCHncIxoq2XWyqFjFQtA "Date changes, stage changes, and value calculations roll up from child tasks to parent tasks.") that the application supports.
* `lag_time` is the amount of time, in days, to delay the start of the dependent task. This value can be positive or negative integers.
{#r_ProjectTaskDependencyValues__ul_btr_y2b_ms}

The values are entered without the curly braces {}. See the examples in the
table.  
Nota:  
You can also edit tasks from the Gantt chart by clicking the relationship line. See [Gantt chart options](https://servicenow-prod.fluidtopics.net/~NZo5a0Sm2BuKjINrPr9VQ "Use the Gantt chart to quickly change task attributes, such as start and end time, rather than opening every Task form and modifying field values one by one.") and [Modify a project task dependency](https://servicenow-prod.fluidtopics.net/kgQcFtSZltsqffHtII57gw "Modify a dependency when editing the tasks that are linked in the dependency, the dependency type, or the lag time.") for details. {#r_ProjectTaskDependencyValues__table_a34_42b_ms__entry__3}

| Dependency type | Example | Additional information |
|-|-|-|
| Finish to start | 1.1fs+0 | The task you are editing starts when task 1.1 is finished. |
| Start to start | 1.1ss+0 | Task 1.1 cannot finish until the task you are editing finishes. |
| Start to finish | 1.1sf+0 | Task 1.1 cannot start until the task you are editing finishes. |
| Finish to finish | 1.1ff+0 | The task you are editing cannot finish until task 1.1 finishes. |
[Tabela 1. Project task dependency values]

{#r_ProjectTaskDependencyValues__table_a34_42b_ms}
**Conceitos relacionados**   

* [Client side planning console](https://servicenow-prod.fluidtopics.net/KaCJm~rOZnXTz2LOHW3DZg "During calculation of project schedule in the planning console, it is possible to build your project structure quickly on the client side (browser) without having to save details in the server for each interaction. It prevents any time lags that occur after you perform any actions in the planning console, and improves the scheduling performance.")
* [Gantt chart](https://servicenow-prod.fluidtopics.net/HZRF0jSRmrpy5ZEE5jAOrQ "A Gantt chart on the planning console is a visual representation of a project timeline that shows start and end dates of tasks, and the dependencies between tasks.")
* [Custom columns in the planning console](https://servicenow-prod.fluidtopics.net/bVXXGv5ivGAxBexUpXB4aQ "In addition to the regular columns that are provided in the base system, as the PPS admin, you can configure which columns appear in the planning console.")
* [Using Planning console - Legacy](https://servicenow-prod.fluidtopics.net/v44qZg77UAOmv3ggCa4Vaw "The planning console is a centralized interface for the Project Management application.")  
**Tarefas relacionadas**   

* [Open the project planning console](https://servicenow-prod.fluidtopics.net/YxIheXCdKThtoS9NZ5aoKw "Access the planning console to perform the planning for the project.")
* [Create a parent-child relationship on the planning console](https://servicenow-prod.fluidtopics.net/CNZmM7kpzmIG~x1jXWf2vA "The WBS section of the planning console allows you to create parent-child relationships for new tasks or move around existing tasks in a new parent-child relationship. The position of a task in the hierarchy and the level of indentation determine the parent-child relationship it has with the tasks above or below it.")
* [Create a dependency from the planning console](https://servicenow-prod.fluidtopics.net/HBOU8kGt9kqIi9ZtxVKw9A "Create a dependency between two tasks on the planning console.")  
**Referência relacionada**   

* [Planning console tasks](https://servicenow-prod.fluidtopics.net/Rvh6uEla03vOPmR_6nbIqQ "You can perform several tasks on the planning console that you can perform on lists and forms, such as creating project tasks and copying projects. You can also perform several tasks unique to the console.")