View default project and project task state categories

  • Versão de lançamento: Australia
  • Atualizado 12 de mar. de 2026
  • 1 min. de leitura
  • View category information for the default project and project task states. In the base system, the states in project and project task inherit the states in Task table.

    Antes de Iniciar

    Role required: admin

    Procedimento

    1. Navigate to All > Dictionary.
    2. Update the filter with the following AND conditions:
      1. [Table] [is] [task]
      2. [Column name] [is] [state]
    3. Run the filter.
    4. Select the task table, and then choose planned_task table in Dictionary Overrides related list.

    Resultado

    The Attributes field displays different states and the categories for a state as shown below. It also displays the default state value for each category.

    close_states=3;4;7,default_close_state=3,default_work_state=2,default_open_state=1,default_skipped_state=7,default_pending_state=-5,pending_states=-5,open_states=1,work_in_progress_states=2