# Create a test plan using Test Board in Test Management 2.0

# Create a test plan using Test Board in Test Management 2.0 {#ariaid-title1}

* Versão de lançamento: Australia
* 
* Atualizado 12 de mar. de 2026
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 1 min. de leitura

Define how to test a product or feature by creating a test plan.

## Antes de Iniciar

Role required: sn_test_management.test_manager

## Procedimento

1. Navigate to AllTest Management 2.0Test Board.
2. Click Create Test Plan.
3. In the form, fill in the fields:  
   {#create-test-plan__table_qv2_x2g_mcb__entry__2}

   | Field | Value |
   |-|-|
   | Name | Unique name for the test plan. |
   | Planned start date | Planned date and time for starting the test plan execution. |
   [Tabela 1. Test Plan form]

   {#create-test-plan__table_qv2_x2g_mcb}
4. Click OK.  
   The Details tab opens.
5. Provide, review, and edit the test plan details.  
   {#create-test-plan__table_er1_ypl_zgb__entry__2}

   | Field | Value |
   |-|-|
   | Planned end date | Planned date and time for ending the test plan execution. |
   | Duration | Estimated duration of test plan. This is the difference between the planned start date and the planned end date. |
   | Number | Automatically generated unique ID number for the test plan. |
   | Owner | Owner who created the test plan. |
   | State | Current state of the test plan. * Pending: Test plan is not yet ready to be performed. * Open: Test plan is ready to be performed. * Work in progress: Test plan is currently being performed. * Closed complete: Test plan has been closed after completion. * Closed incomplete: Test plan has been closed without completion. * Closed skipped: Test has been closed without being performed. {#create-test-plan__ul_pbm_zkm_zgb} |
   | Description | Description of the test plan. |
   [ ]

   {#create-test-plan__table_er1_ypl_zgb}  
   Nota:  
   The Progress section displays the overall status of the test plan indicating the percentage of tests in the test plan that have passed, failed, or been blocked.