# Add dependencies for Agile Development 2.0 stories

# Add dependencies for Agile Development 2.0 stories {#ariaid-title1}

* Versão de lançamento: Australia
* 
* Atualizado 12 de mar. de 2026
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 1 min. de leitura

Add prerequisite and dependent items for stories in Agile Development 2.0 so
that you can visualize these dependencies on the scrum planning board and plan your sprints
accordingly.

## Antes de Iniciar

Role required: scrum_story_creator, scrum_story_editor

## Procedimento

1. Navigate to AllAgile DevelopmentStories.
2. Open the story to which you want to add dependencies.  
   Alternatively, you can use the scrum program board from the Agile board to open your story and add dependencies.
3. Add dependencies to the stories using the Prerequisite Stories or Dependent Stories related lists.  
   * Prerequisite Stories is the list of all stories that must be complete before the current story.
   * Dependent Stories is the list of all stories that depend on the completion of the current story.
   {#Add-dependencies-to-stories__ul_swy_q1n_hcc}
4. Select Save and then select Update.

## O que Fazer Depois

You can visually analyze the dependencies of the stories using the scrum program board to help with your sprint planning.

1. Navigate to AllAgile DevelopmentAgile BoardProgramPlanning
2. Use the dependencies icon (![Story dependencies icon]()) to show or hide dependencies between stories.
{#Add-dependencies-to-stories__ol_pzl_pf4_g5b}  
Nota:  
Access to the Scrum program board is available only with the Scrum Programs plugin (com.snc.sdlc.scrum_program).