Update the dependency details for tasks from Project Workspace

  • Versão de lançamento: Australia
  • Atualizado 12 de mar. de 2026
  • 1 min. de leitura
  • Update the details of the dependency including its type and lag time from Project Workspace.

    Antes de Iniciar

    Role required: it_project_manager

    Procedimento

    1. Open a project from the home page of Project Workspace.
      For information, see Access the new Project Workspace.
    2. Open the dependency side panel in one of the two ways.
      OptionAction
      From the data grid From the dependency column, select the dependency of the task.
      From the timeline view Select the dependency line.
    3. Edit the fields.
    4. Select Update.