Track progress of scrum tasks for a sprint in Agile Development 2.0

  • Versão de lançamento: Australia
  • Atualizado 12 de mar. de 2026
  • 1 min. de leitura
  • Use the Sprint Tracking tab of the Agile board in Agile Development 2.0 to track the progress of scrum tasks for the stories from your current sprint.

    Antes de Iniciar

    You must be a member of an agile group to access the board.

    Role required: scrum_user or scrum_admin

    Por Que e Quando Desempenhar Esta Tarefa

    Use the Task board view of the Sprint Tracking tab to check the state of your scrum tasks for the current sprint. On the board, each story is a collapsible section. Tasks for each story are shown as cards in these sections, with their states indicated as lanes.

    You can move the task cards into different lanes or add new task for a story, to make real-time updates during scrum calls or other status meetings.

    Procedimento

    1. Navigate to All > Agile Development > Agile Board.
    2. Click the Sprint Tracking tab.
    3. From the Task board view, review the states of the scrum tasks of all stories scheduled for the current sprint.
    4. Change the state of a scrum task by moving the task from one lane to another.
    5. Add a scrum task to a specific lane.
      1. Click + Add Card.
      2. On the form, fill in the fields and click Submit.