Request extension of an allocated resource plan

  • Versão de lançamento: Australia
  • Atualizado 12 de mar. de 2026
  • 1 min. de leitura
  • As a project manager, you can request the extension of an allocated resource plan.

    Antes de Iniciar

    Importante:
    Resource plans in Resource Management will no longer be available for new customers from future releases.

    You're encouraged migrate your existing resource plans to work on resource assignments which offers more flexibility and start using Resource Management Workspace.

    Resource requester can extend a resource assignment using Resource Management Workspace.

    Role required: it_project_manager, resource_user

    Por Que e Quando Desempenhar Esta Tarefa

    Assume that a project, which has resources allocated, gets delayed by one month. As a project manager, you can request for the extension of the resource plan if you need resources for the period. This option is available only when the resource plan is in the Allocated state.

    Procedimento

    1. Navigate to All > Resource > Resource Plans > All.
    2. Open a resource plan and select Request Extension.
    3. On the Request Extension from, fill the fields.
      For a description of the field values, see Request Extension form.

    Resultado

    The end date of the resource plan is updated and the Extension field is set to Requested.

    O que Fazer Depois

    Allocate resources for the extended period.