Realign or synchronize the resource assignment dates with the project task dates. This synchronization helps to schedule and align the resource assignments with the timeline of project
task.
Before you begin
Role required: it_project_manager
Procedure
-
Navigate to and open a project.
-
From the project planning pane, double-click the Planned start date or Planned end date of a project task to edit the field.
Use the Resources not synced icon
to synchronize the resource assignments dates with the project dates at a project level.
-
Select Ok.
If the sn_pw.resource_assignment_auto_sync_enabled system property is set to true, then the resources sync automatically in the background. The bottom resource pane updates without any action, and
the manual sync icon (resources not synced icon) is hidden since it's no longer needed. The default value is true. When the property is set to false, manual sync via the icon is still required and resources not
synced icon is visible. You must have the pps_admin role to enable this property.
Alternatively, select more actions context menu and select Realign resource assignments to synchronize the resource assignments dates with the project dates at a project level.
Result
The resource assignments dates are synchronized with the project task dates.