Realign resource assignments with demand

  • Release version: Australia
  • Updated March 12, 2026
  • 1 minute to read
  • Planning and execution of your roadmap involves change in priority or timelines of your work. In such cases, you can adjust the resource assignment dates to match with the latest dates of your demands.

    Before you begin

    Migrate resource plans to resource assignments

    Role required: it_demand_manager

    Procedure

    1. Navigate to All > Demand > Demands > All.
    2. Open the required demand.
    3. Change the Approved start date and Planned start date to meet your organizational priorities.
    4. Select Save.
    5. Select the Realign assignments to demand related link.

    Result

    In the Resource assignments related list, you can see the Start date of the resource assignments aligned with the demand start dates.