Project currency in cost and benefit plans

  • Release version: Australia
  • Updated March 12, 2026
  • 1 minute to read
  • The currency fields in cost and benefit plans defaults to the project currency of the project.

    Entered currency field in cost and benefit plans

    The Entered Currency field of the cost plan defaults to the project currency of the project if multicurrency plugin is installed, irrespective of the views – default or functional currency. However, if multicurrency plugin is not installed, the Entered currency field of the cost plan defaults to the functional currency of the project.

    Similarly, the Entered Currency field of the benefit plan defaults to the project currency of the project if multicurrency plugin is installed, irrespective of the views – default or functional currency. However, if multicurrency plugin is not installed, the Entered Currency field of the benefit plan defaults to the functional currency of the project.