# Create resource assignments

# Create resource assignments in Resource Management Workspace {#ariaid-title1}

Release version: Australia  
Updated March 12, 2026  
![](https://www.servicenow.com/docs/portal-asset/ico-clock) 1 minute to read  
Create and assign resource assignments and operation resource assignments from Resource Management Workspace.

## Before you begin

Role required: resource_user, resource_manager, It_project_manager

## Procedure

1. Navigate to WorkspacesResource Management Workspace.
2. Select the Resource cards icon (![Resource cards icon.]()) from the menu and open a resource card.
3. Create resource assignments using one of the following options.

   | Option | Procedure |
   | Create a resource assignment | 1. Select New or select New Resource Assignment from the more actions list. 2. On the New Resource Assignment form, fill in the fields.For a description of the field names, see [New Resource Assignment form](https://servicenow-prod.fluidtopics.net/~YdV5riufS0dTwuT6tWt6Q "Fill in the following fields to create a resource assignment using Resource Management Workspace."). {#create-ra-rmw__ol_qqm_yxx_bcc} |
   | Create operational resource assignment | 1. Select New operational Assignment from the more actions list. 2. On the New Operational Assignment form, fill in the fields.For a description of the field names, see [New Operational Assignment form](https://servicenow-prod.fluidtopics.net/uBeRmavurieF8p8ENDmpYA "Fill in the following fields to create a operational assignment using Resource Management Workspace."). {#create-ra-rmw__ol_gpp_pcy_bcc} |
   |-|-|

   {#create-ra-rmw__choicetable_ibq_nxx_bcc}
4. Select Submit.

## Result

Resource assignment is created. You can filter and view this assignment in the lower tray of Unassigned tasks.

An assignment made for a resource from the resource board must be within the selected date range. If so, it shows up nested under the selected resource in real-time.