Manage your team backlog
Manage, evaluate, prioritize, and sequence stories in your team backlog.
Before you begin
- Program, to which the team belongs, must contain an active program increment.
- The tab displays only the sprints of the current program increment.
Role required: scrum_product_owner, scrum_master, safe_product_owner, or safe_scrum_master
Procedure
Perform sprint planning
Perform sprint planning by evaluating stories in the backlog, selecting stories for the sprint, and estimating work effort for the stories.
Before you begin
The tab displays only the sprints of the current program increment.
About this task
In SAFe, the main portion of sprint planning occurs during the Big Room Planning process. The team backlog and the sprint planning portion of it is designed for refinement sessions. Though the overall plan of each sprint of a program increment already exists, the team still has sprint planning sessions every two weeks to add any missing stories and adjust the initial plan.