Analyze adherence and conformance from the time worked summary
View the time worked summary of your team members to determine whether your teams are adhering to planned schedules. You can also use historical adherence, a reporting view of real-time adherence, to see how well your agents have followed their schedules in the past.
Before you begin
Role required: sn_shift_planning.admin
About this task
Adherence and conformance calculations are based on a defined configuration and your
agents' actual and planned work schedules. For more information, see Setting up scheduling in Workforce Optimization for Field Service.
Note:
Your administrator can
disable schedule adherence or change the configuration for adherence and
conformance. For more information, see Configure properties for schedule adherence and conformance.
Procedure
Example
- Shift time begins at 8 a.m. and goes to 4 p.m. = 8 hours
- Planned time = 8 hours = 480 minutes​
- Clocks in 8 a.m. and clocks out at 12 p.m. for a break. Back from the break, clocks in at 12:30 p.m. and clocks out at 4 p.m.
- Minutes worked in shift = 480 - 30 = 450 minutes​
- Schedule adherence= (minutes worked in shift/scheduled shift time in minutes + overtime) = 450/(480+65) = 82.57%
- Conformance= (minutes worked in shift + overtime)/scheduled shift time in minutes = (450 + 65) / 480 = 107.29 percent​.
Note:
Fatima Alonzo is adherent because the schedule adherence and conformance are
within the threshold. To see which agents are non-adherent, look for the numbers
highlighted in red.