Adjust workplace contract in Workplace Central

  • Freigeben Version: Australia
  • Aktualisiert 12. März 2026
  • 1 Minute Lesedauer
  • Change the start date, end date, or amount to be paid for an contract in active state.

    Vorbereitungen

    Role required: sn_wsd_la.workplace_central_user, sn_wsd_la.manager or sn_wsd_la.admin

    Warum und wann dieser Vorgang ausgeführt wird

    To adjust a contract, the State should be Active.

    Prozedur

    1. Navigate to Workspaces > Workplace Central.
    2. Click Adjust.
    3. Complete the form.
      Tabelle : 1. Adjust the contract values form
      Field Description
      Start Date Date on which the contract takes effect.
      End Date Date on which the contract expires.
      Payment Amount Total amount paid for the contract. If the contract has one or more rate cards, this field shows the total of all rate card base costs.
    4. Click Submit Adjustments.