Lead time calculations
Summarize
Summary of Lead time calculations
Lead time calculations in ServiceNow's purchasing process measure the total duration required to fulfill a purchase order for a supplier product. This total lead time includes sourcing, supplier onboarding, purchasing, and shipping times. These metrics help organizations accurately estimate procurement timelines and manage supplier performance effectively.
Show less
Supplier Onboarding Time
This represents the average days to onboard a new supplier for a product category, starting with a default of 15 days. It is updated automatically based on actual onboarding task durations from completed purchase requisitions. Calculations aggregate durations across purchase requisitions related to product categories, always rounding up decimals.
Sourcing Time
Sourcing time is the average days required to source a product from a supplier, initially set to 3 days. It updates dynamically from completed sourcing requests, averaging durations at supplier product, product model, and product category levels. Sourcing time is 0 if the product category's spend categorization is Not Addressable. Purchase lines closed as Canceled do not update sourcing times. Decimal results are rounded up.
Purchasing Time
Purchasing time reflects the average days to complete the purchase requisition workflow and generate purchase orders, with a default of 5 days. It updates based on actual durations of completed purchase requisitions (excluding Blanket orders) and averages are computed across supplier products, product models, and product categories, rounding up decimals.
Shipping Time
Shipping time estimates days to deliver a supplier product to the destination. It is sourced directly from the supplier's shipping time and updates for all products from that supplier when changed. For supplier products integrated via third-party systems, shipping time is pulled from the integration data. Shipping time is always 0 for service-type products.
Total Lead Time
Total lead time sums the relevant components depending on whether sourcing and supplier onboarding are required:
- If both required: onboarding time + sourcing time + purchasing time + shipping time
- If only sourcing required: sourcing time + purchasing time + shipping time
- If only onboarding required: onboarding time + purchasing time + shipping time
- If neither required: purchasing time + shipping time
This total is recalculated whenever related values change and after each purchase requisition completion, considering data from the past 12 months.
Practical Implications for ServiceNow Customers
- These calculations enable accurate estimation and tracking of procurement lead times at multiple product hierarchy levels, improving supplier and purchasing efficiency.
- Automatic updates based on actual procurement data ensure that lead times reflect current operational realities.
- Understanding these metrics helps optimize purchasing workflows and supplier onboarding processes within ServiceNow.
- Customizable default values provide flexibility to align with organizational procurement policies.
Lead time (in days) of a supplier product consist of the time for sourcing, supplier onboarding, purchasing, and shipping for a supplier product, product model, or a product category. Each of these durations are used to calculate the total lead time which determines the number of days to execute a purchase order.
Supplier onboarding time
Supplier onboarding time indicated the average number of days to onboard a new supplier for a product of a category. The initial default value is 15 days, as defined in the sn_shop.default.supplier.onboard.time property of the purchasing properties table.
When a purchase requisition is created for a supplier product, it can have a purchasing task of type supplier onboarding. Over time, as purchase requisitions are completed, the onboarding time for a supplier is updated automatically as follows:
For a product category: Supplier onboarding time = Sum [Actual Duration of supplier tasks for purchase requisitions with purchase lines in a category]/Number of Supplier onboarding tasks.
| Purchase Requisition A for Supplier A | Purchase Requisition B for Supplier B | Purchase Requisition C for Supplier C |
|
|
|
| Calculated supplier onboarding time in days | ||
Note: If the calculation produces a decimal, always round up regardless of the
value. |
||
Sourcing time
Sourcing time indicates the average number of days taken to source a product from a supplier, if sourcing is required for products of a category.
The initial default value is three days, as defined in the sn_shop.default.sourcing.time property of the purchasing properties table. This value is updated over time, as sourcing requests for a supplier product are completed.
- The actual duration values of all sourcing requests for supplier products are considered. An average of these values is calculated. This average is the new default sourcing time for this supplier product.
- When the sourcing time is updated for a supplier product, it is recalculated for the related product model as an average of the sourcing times of all its supplier products.
- When the sourcing time is updated for a product model, it is recalculated for the related product category as an average of the sourcing times of all its product models.
For any new product model, the sourcing time is the same as its referenced model category. For any new supplier product, the sourcing time is the same as its referenced product model.
- If Spend categorization of a product category is Not Addressable, the sourcing time is always 0.
- If the Purchase Line is of the state Closed Canceled, it indicates that sourcing did not occur for that purchase line. In this case, the average sourcing time of the supplier product is not updated.
Example calculation of sourcing time:
| Sourcing Request A for MacBooks | ||
| Actual duration = 16 days | ||
Purchase line 1 – Reseller A MacBook
|
Purchase Line 2 – Reseller B MacBook
|
Purchase Line 3 – Apple MacBook (assume current sourcing time is 11 days)
|
| Sourcing Request B for Lenovo Think Pads | ||
| Actual duration = 22 days | ||
Purchase line 4 – Reseller A Lenovo Think Pad
|
Purchase Line 5 – Reseller B Think Pad
|
|
| Calculated sourcing time in days | ||
Note: If the calculation produces a decimal, always round up regardless of the
value. |
||
Purchasing time
Purchasing time indicates the average number of days taken to complete the purchase requisition workflow and create purchase orders for products in a category.
The initial default value is five days, as defined in the sn_shop.default.purchasing.time property of the purchasing properties table. This value is updated over time, as purchase requisitions for a supplier product are completed.
- The actual duration values to complete all purchase requisitions for supplier products are considered. An average of these values is calculated. This average is the new default purchasing time for this supplier product.
- When the purchasing time is updated for a supplier product, it is recalculated for the related product model as an average of the purchasing times of all its supplier products.
- When the purchasing time is updated for a product model, it is recalculated for the related product category as an average of the purchasing times of all its product models.
| Purchase Requisition A for Reseller A | Purchase Requisition B for Reseller B | Purchase Requisition C for Reseller B | Purchase Requisition D for Reseller A |
|
|
|
|
| Calculated purchasing time in days | |||
Note: If the calculation produces a decimal, always round up regardless of the
value. |
|||
Shipping time
Shipping time indicates the estimated number of days taken to ship a supplier product to a delivery location. This value is retrieved from the shipping time of a supplier.
Whenever the shipping time for a supplier is updated, the shipping times of all the supplier products belonging to that supplier reflect the same.
Total lead time
Total lead time indicates the numbers of days taken to execute the purchase order of a supplier product and deliver it to the employee.
- If sourcing and supplier onboarding are required,
Total lead time = [Supplier onboarding time from the referenced product category] + [Sourcing time of the supplier product] + [Purchasing time for the supplier product] + [Shipping time of the supplier product].
- If sourcing is required but supplier onboarding is not required,
Total lead time = [Sourcing time of the supplier product] + [Purchasing time for the supplier product] + [Shipping time of the supplier product].
- If sourcing is not required and supplier onboarding is required,
Total lead time = [Supplier onboarding time from the referenced product category] + [Purchasing time for the supplier product] + [Shipping time of the supplier product].
- If sourcing and supplier onboarding are not required,
Total lead time = [Purchasing time for the supplier product] + [Shipping time of the supplier product].
The total lead time of a supplier product is recalculated every time the values of the above fields on the supplier product form are updated.