Create a milestone

  • Freigeben Version: Australia
  • Aktualisiert 12. März 2026
  • 1 Minute Lesedauer
  • A milestone is a project task with a duration of zero (0). Use milestones to mark key dates in your project, such as key decision points, approvals, and holidays. Milestones are treated like any other project task and you can create dependencies between tasks and milestones.

    Vorbereitungen

    Role required: it_project_manager

    Warum und wann dieser Vorgang ausgeführt wird

    Hinweis:
    Milestones cannot be shared between projects unless one project is nested under another project.

    Prozedur

    1. Create a project task and give the Duration field a value of 0.
    2. Open the planning console Gantt chart and verify that it appears as a diamond.
      You can also convert a task to milestone through Planning console tasks.

    Ergebnisse

    Abbildung : 1. Milestone
    Milestone example