Initiate guided test execution

  • Freigeben Version: Australia
  • Aktualisiert 12. März 2026
  • 1 Minute Lesedauer
  • Create assessments for the assigned testers of each test case in a test plan by notifying them to start testing. The test manager can initiate guided test execution from the Test Plan form.

    Vorbereitungen

    Warum und wann dieser Vorgang ausgeführt wird

    If you are using guided test execution, you can notify testers to start testing directly from the Test Plan form. The testers are notified through an email about their assigned assessments. Testers can find these assessments by navigating to Self-Service > My Tests or Self-Service > My Assessments.

    Prozedur

    1. Navigate to Test Management > Test Execution > Test Plans.
    2. Open the test plan that you want to start executing.
    3. From the Test Cases related list, use the Assigned to field to assign the test cases to testers.
    4. Click the Notify Tester related link.
    5. Enter a date in the Testing end date field and click OK.
      This date is used as the due date for the assessment.

    Ergebnisse

    Assessments for each tester are created and email is sent to each tester with the assessment and testing details. After the testers are notified through the email, the Notify Tester related link on the Test Plan form changes to Cancel test execution.