Create and manage dependencies between work items in EAP
Draw work item dependencies in real-time across teams and iterations and visually analyze them while you collaborate using the Planning board in Enterprise Agile Planning.
Vorbereitungen
Role required: sn_apw_advanced.eap_user
Warum und wann dieser Vorgang ausgeführt wird
This task is explained using stories in an Agile Release Train (ART) as an example, which has Planning Interval (PI) as its calendar. The same guidance applies to creating, updating, and deleting dependencies for work items of an Agile Team, Solution Train, or Portfolio.
- A story that has a dependency on it by another story is called a prerequisite story.
- A story that is dependent on another story is called the dependent story.