Add dependencies for Agile Development 2.0 stories
Add prerequisite and dependent items for stories in Agile Development 2.0 so that you can visualize these dependencies on the scrum planning board and plan your sprints accordingly.
Vorbereitungen
Role required: scrum_story_creator, scrum_story_editor
Prozedur
Nächste Maßnahme
You can visually analyze the dependencies of the stories using the scrum program
board to help with your sprint planning.
- Navigate to
- Use the dependencies icon (
) to show or hide dependencies between stories.
Hinweis:
Access to the Scrum program board is available only with the Scrum Programs
plugin (com.snc.sdlc.scrum_program).