Assign a project schedule

  • Freigeben Version: Australia
  • Aktualisiert 12. März 2026
  • 1 Minute Lesedauer
  • Without an assigned schedule, a project calculates a day as a full 24 work hours. To schedule tasks by a more realistic work day, assign a schedule to the project. If the schedules provided in the base system do not suit your needs, define a new one.

    Vorbereitungen

    Role required: it_project_manager

    Prozedur

    1. Open a project.
    2. If the Default view is active, right-click the header bar and select View > Advanced.
    3. Select a schedule in the Schedule field and select Save.