Use the Analytics Project manager

  • Freigeben Version: Australia
  • Aktualisiert 12. März 2026
  • 1 Minute Lesedauer
  • The Analytics Project manager shows the time card reports for the selected projects.

    Warum und wann dieser Vorgang ausgeführt wird

    Wichtig:
    Starting with Xanadu release, Project Manager Dashboard is renamed to Analytics Project manager for new customers.

    Vorbereitungen

    Role required: it_project_manager, timecard_admin

    Prozedur

    1. Navigate to All > Time Sheets > Analytics Project manager.
    2. Select a project and date range from the Project and Date choice lists.
    3. Review the displayed reports and take necessary actions, if required.