Update the dependency details for tasks from Project Workspace

  • Freigeben Version: Australia
  • Aktualisiert 12. März 2026
  • 1 Minute Lesedauer
  • Update the details of the dependency including its type and lag time from Project Workspace.

    Vorbereitungen

    Role required: it_project_manager

    Prozedur

    1. Open a project from the home page of Project Workspace.
      For information, see Access the new Project Workspace.
    2. Open the dependency side panel in one of the two ways.
      OptionAction
      From the data grid From the dependency column, select the dependency of the task.
      From the timeline view Select the dependency line.
    3. Edit the fields.
    4. Select Update.