Create a project task in the project workbench

  • Freigeben Version: Australia
  • Aktualisiert 12. März 2026
  • 1 Minute Lesedauer
  • Create a project task for a waterfall phase.

    Vorbereitungen

    Role required: it_project_manager

    Warum und wann dieser Vorgang ausgeführt wird

    While creating a project task in the project workbench, the time constraint type is defaulted based on the project type.
    • For a manual project, the default constraint is Start On and cannot be changed.
    • For an automatic project, the default constraint is Start ASAP and can be changed to Start On if required.
    • When the constraint is Start ASAP, the Planned start date is disabled.
    • When you create an agile phase and associate a sprint, the start date of the task is set from the sprint start date and the constraint becomes Start On automatically.

    Prozedur

    1. Select a waterfall phase in the project workbench timeline.
    2. Select New in the detail view.
    3. Fill out the Project Task form.
    4. Select Submit.