Modify a project task dependency

  • Freigeben Version: Australia
  • Aktualisiert 12. März 2026
  • 1 Minute Lesedauer
  • Modify a dependency when editing the tasks that are linked in the dependency, the dependency type, or the lag time.

    Vorbereitungen

    Role required: it_project_manager

    Warum und wann dieser Vorgang ausgeführt wird

    Project task dependencies are saved on the Planned Task Relationship [planned_task_rel_planned_task] table. You can access dependencies from the planning console.

    Prozedur

    1. Double-click a dependency on the Gantt chart of the planning console.
    2. On the form, fill in the details.

      For more information, see Planned Task Relationship form.

      Abbildung : 1. Planned Task Relationship form
      Planned Task Relationship form
    3. Select Update.
      You can view dependencies in the Project Task related list on a Project or Project Task form and from the Project Tasks list on the workbench. These columns show the dependencies: