Request resources

  • Freigeben Version: Australia
  • Aktualisiert 12. März 2026
  • 1 Minute Lesedauer
  • After you create a resource plan, request resources from the resource manager.

    Vorbereitungen

    Role required: it_project_manager, resource_user

    Warum und wann dieser Vorgang ausgeführt wird

    Hinweis:
    If the resource type in the resource plan is a group, you can request resources only if that group has active members.

    Prozedur

    1. Navigate to All > Resource > Resource Plans > All.
    2. Open a resource plan that is in the Planning state.
    3. Select Request.

    Ergebnisse

    The resource plan moves to the Requested state and is ready for review by the resource manager.