Move a resource assignment in Project Workspace
Move the resource assignment to a new start and end dates to accommodate changes in task scheduling or resource allocation. Shift assignments to balance workloads across resources and avoid over-allocation.
Vorbereitungen
Role required: resource_user, resource_manager
Warum und wann dieser Vorgang ausgeführt wird
- When you move an assignment to a new start and end dates, the initial requested or approved efforts are retained for the latest duration.
- When an assignment is moved, the Ready for review state is retained and the assignment remains accessible to resource managers for work allocation.
- You cannot move a resource assignment if actuals efforts are entered for the work.
- New assignment dates should be within the task duration dates.