Manage project stories in the project workbench

  • Freigeben Version: Australia
  • Aktualisiert 12. März 2026
  • 1 Minute Lesedauer
  • If Project Portfolio Management and Agile Development 2.0 are activated, the project manager can manage the stories in a project from the project workbench.

    Vorbereitungen

    Activate Project Portfolio Management and Agile Development 2.0 plugins.

    Role required: it_project_manager

    Warum und wann dieser Vorgang ausgeführt wird

    Manage stories in your project using the Manage Stories option in the Project Workbench.

    Prozedur

    1. In the project workbench header, select the options icon (Options icon) and then select Manage Stories.
      The Backlog section of the Agile Board opens in a new tab.
    2. Select a story to open the Story form in the pop-up window, or select New to create a new story.
    3. Fill in the fields on the Story form.
    4. Select Update or Submit.