Create a baseline

  • Versão de lançamento: Australia
  • Atualizado 12 de mar. de 2026
  • 1 min. de leitura
  • A Planned Task Baseline is a record of the start and end times of the planned task at a particular moment in time.

    To create a baseline, navigate to the form of the top planned task and select the Create a Baseline related link:
    Figura 1. Create baseline
    Create baseline for the current task.
    To view the baseline, configure the related lists to add a related list of baselines:
    Figura 2. Baselines tab
    Baseline related list

    The baseline can be viewed on a Gantt Chart using the related link.