Generate labor costs

  • Release version: Xanadu
  • Updated August 1, 2024
  • 1 minute to read
  • Generate labor costs to view the expenses of resources using resource assignments and cost plans.

    Before you begin

    Role required: it_demand_manager

    Procedure

    1. Navigate to All > System Definition > Scheduled Jobs.
    2. Open the Generate labor costs for demands and projects scheduled job.
    3. Select Active and on the Scheduled Script Execution form, fill the fields.
      For a description of the field names, see Scheduled Script Execution Form.
    4. Select Update.
      Tip:
      Alternatively, as an admin, you can activate and define a scheduled job to generate labor costs at required frequency. For more information on how to activate a scheduled job, see Activate a scheduled job to generate labor costs.