# Parent-child task relationships

# Parent-child task relationships {#ariaid-title1}

* Release version: Xanadu
* 
* Updated August 1, 2024
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 1 minute to read

If a task is relatively large and requires several users with different skills to
manage, break the task into subtasks and create parent-child relationships. A child task is a
relatively smaller, manageable size of work.

When you group child tasks together under a parent, values such as Estimated cost aggregate and roll up to the parent task. So the parent task takes on the form
of a summary task or rollup task for its child tasks. Planned start date
and Planned end date rollup occurs when you create child tasks: the
duration of the parent automatically adjusts to cover its child tasks.

A parent-child relationship is different from a dependency relationship. In a dependency, one
task must finish before another begins. In a parent-child relationship, any number of tasks can
be nested under a parent task with or without any dependencies. When you create a parent-child
relationship, the parent task number is saved in the Parent field in the
Project Tasks table. All project management tasks have a parent: either another project task or
the project itself.

Unlike a dependency, a parent-child relationship is not saved as a record in any table. The
only modification that takes place when a parent-child relationship is modified is the
Parent field in the child task record.

You can create predecessor-successor relationships between child tasks with different parents,
between two different parent tasks, or between a child task and another parent task. However, if
the predecessor task finishes after the successor task starts, creating a dependency between
child tasks that have different parents is not allowed.  
Note:  
On the Gantt chart, you can drag-and-drop the parent task to move the entire hierarchy to a new location on the schedule.
* **[Create a parent-child relationship on the Project Task form](https://servicenow-prod.fluidtopics.net/CntRIGRl9NmB8~pN3ifQmQ)**   
  You can create a child task from any project task form.
* **[Time constraints in parent-child relationships](https://servicenow-prod.fluidtopics.net/FOyqWsHQ1Rh4OQtiJdYmMA)**   
  Parent-child task relationships have several effects on task time constraints.