# Compare financial baselines of a project

# Compare financial baselines of a project {#ariaid-title1}

* Release version: Xanadu
* 
* Updated August 1, 2024
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 2 minutes to read

You can compare baselines to review the variances in the financial data of a project
and see what changed.

## Before you begin

Role required: it_project_manager

## About this task

You can [create](https://servicenow-prod.fluidtopics.net/rpnMdmmWB4r_uM8689QhCQ "Create a schedule baseline and financial baseline of a project. A schedule baseline captures planned dates of all tasks and milestones at a particular moment in time. A financial baseline captures benefit and financial metric information (snapshot of cost plan, benefit plan, and project-level financial metrics) at a particular moment in time.") multiple baselines at various stages of a project, for example,
at the end of each phase or after every calendar month or quarter. Each baseline
captures the financial data of the project at a particular moment, providing a basis
from which you can identify and review the changes made to the project. Having
multiple baselines and comparing them helps you track the performance of your
projects.

## Procedure

1. To compare the financial baselines of a project, use one of the following options.

   | Option | Steps |
   | From the Project Workspace | 1. Navigate to ProjectProjectsProject Workspace. 2. Open a project. 3. Click the Financials tab. 4. Click the baseline information icon (![Baseline information icon]()) and then select Compare Baselines. {#compare-baselines-of-project__ol_jz2_t4y_tfb} |
   | From the Project form | 1. Navigate to ProjectProjectsAll. 2. Open a project. 3. On the Project form, click the Cost Plans or Benefit Plans related list. 4. Click Manage. 5. On the Financials tab, click the baseline information icon (![Baseline information icon]()) and then select Compare Baselines. {#compare-baselines-of-project__ol_kyc_spy_tfb} |
   | From the Baseline form | 1. Navigate to ProjectProjectsAll. 2. Open a project. 3. On the Project form, click the Baseline related list. 4. Open a baseline. 5. On the Baseline form, click the View Financial Baseline related link. {#compare-baselines-of-project__ol_a5n_mpy_tfb} |
   |-|-|

   {#compare-baselines-of-project__choicetable_wgp_h4y_tfb}
2. On the Financial Baseline form, select the baselines you want to compare from the two choice lists.  
   By default, the current and the most recent baselines are selected.
3. Click Compare.  
   The comparative data of the baselines display in the following two sections:
   * The Financial Baseline Summary section displays four widgets: the first two widgets contain the financial data of the two baselines, the third widget contains their variance, and the fourth widget contains the actual costs to date of the project.
   * The Financial Baseline Details section displays the cost plans and benefit plans of the two baselines in two different grids. Each plan type has two rows corresponding to each baseline data.  
     Note:  
     Click the baseline legend icon (![Baseline Legend info icon.]()) to see the color code of rows representing each baseline.
   {#compare-baselines-of-project__ul_w4d_q5t_bgb}
4. **Optional:** Review additional fields or reorganize the comparative data on the form.  
   * To show or hide additional fields on the widgets in the Financial Baseline Summary section, click the configuration icon (![Configuration icon]()) and select the field names.

     The selected field
     preferences are saved and are available when you reopen the
     Financial Baseline form. To reset to the default widget layout,
     click Reset to defaults.
   * To view cost plan or benefit plan comparative data in yearly, quarterly, or monthly format, click the Year or Quarter or Month views respectively.
   * To toggle viewing the Financial Baseline Summary section, click the Collapse icon (![Collapse icon]()) or Expand icon (![Expand icon]()).
   {#compare-baselines-of-project__ul_grp_t3j_pgb}

*[\>]: and then