# Types of external dependencies

# Types of external dependencies {#ariaid-title1}

* Release version: Xanadu
* 
* Updated August 1, 2024
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 1 minute to read

The Project management application supports two types of external dependencies - hard
and soft.

The type of external dependency can be set during [adding a dependency](https://servicenow-prod.fluidtopics.net/Xo48~rz1vvUXnMPn1HQKqg "Add an external dependency between two projects on the planning console. Use the work breakdown structure (WBS) column of the planning console to create a dependency between the different projects tasks.") between two projects tasks on the planning console.

## Hard dependencies

In a hard dependency, any changes made in the predecessor project are automatically propagated to the successor project. A [notification](https://servicenow-prod.fluidtopics.net/JWdxDKc2TP_EZ77I4qeYaw#r_PlanningConsoleTasks__table_ukw_ftd_2s) for the changes made is triggered in the successor project. The following image shows the process flow for a hard dependency type:Figure 1. External hard dependency

## Soft dependencies

In a soft dependency, any changes made in the predecessor project trigger a notification in the successor project. As the project manager of the successor project, you can choose to accept or reject the changes in the notification. If you accept the notification changes, the changes in the predecessor project are synced to the successor project and the project is recalculated. If you reject the notification changes, the changes are not propagated to the successor project. The following image shows the process flow for a soft dependency type:Figure 2. External soft dependency
**Related tasks**   

* [Add an external dependency on planning console](https://servicenow-prod.fluidtopics.net/Xo48~rz1vvUXnMPn1HQKqg "Add an external dependency between two projects on the planning console. Use the work breakdown structure (WBS) column of the planning console to create a dependency between the different projects tasks.")