# Basics of Project Management

# Basics of Project Management {#ariaid-title1}

* Release version: Xanadu
* 
* Updated August 1, 2024
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 6 minutes to read

A project is any planned, collaborative effort that is designed to achieve an
objective. The Project Management application not only helps you plan and track projects,
it integrates with other applications.
There are several paths available to manage a project. The best path usually depends on business needs. The phases in the graphic are designed to get a project up and running with the minimum amount of effort:Figure 1. Project phases

## Set up the project

Setting up a project involves deciding on an
approach for creating and linking project tasks. It also involves creating the necessary
users and groups in ServiceNow so you can assign them to project tasks.
Plan the project

Before creating a project, consider the following questions and
issues:

* Do you want a top-down or bottom-up approach to tasking? Top-down tasking involves
  creating a project first, then identifying major project phases. Later on, phases can be
  broken down into tasks and subtasks. The emphasis is on creating estimates for
  high-level items such as phases and parent tasks and then building the project down from
  there toward a more detailed level. Use caution when creating tasks for top-down
  tasking. Creating a task under a project that has a start-on date later than the start
  date of the project, the project shifts to the later start date. The Project Management application supports bottom-up tasking better.

  Bottom-up
  tasking involves creating several sets of small tasks and estimating task items such as
  effort, cost, and duration. These estimations are then aggregated into high-level parent
  tasks (rollup tasks) and phases. The emphasis is on estimating smaller chunks of work as
  accurately as possible first, then letting those estimations roll up into parent tasks,
  phases, and the project itself.
* Is the project part of a larger portfolio of projects? Also consider [portfolio planning](https://servicenow-prod.fluidtopics.net/ksSDhsYTir06FbvFJW2xDA "With the ServiceNow Portfolio Management application, you can create portfolios which are collections of related programs, projects, and demands. You can then perform financial planning and monitor the status and progress of these portfolios.") and
  how the project relates to similar projects or initiatives.

* What types of dependencies do the tasks have with other tasks? The Project Management application supports various dependencies. See: [Project task
  relationships and dependencies](https://servicenow-prod.fluidtopics.net/19ZkzZ1W90OCBNOQbAt65g "The Project Management application enables you a create parent-child relationships between tasks and dependencies, such as finish-to-start and finish-to-finish, between tasks.").

* Can milestones and project baselines help manage a project? A milestone is a project
  task with a duration of 0. Use milestones to indicate important dates in a project. If
  necessary, create dependencies between tasks and milestones so that a task does not
  start until a milestone has been reached.

  A baseline is a snapshot of the current
  planned start and end dates at the time the baseline was created for each task. A line
  appears under each task on the Gantt chart for the original planned start and end dates.
  The line appears shifted to the left or right depending on whether the task was started
  early or late. If tasks slip to later dates, the baseline indicator provides an easy way
  to see how severe the delays are.
* Have the necessary skills, groups, and resources been created in ServiceNow? If
  project tasks are assigned to different groups or individual resources with the required
  skills, create users and groups and configure the Skills Management
  application.

* Does an existing incident, problem, or change justify creating a project to track it? Of these record types, a change is most likely to lead to activities that are tracked
  as a project.

* Do you want to track project costs? Estimate group resource costs before starting the
  project. Then track the actual cost of each user resource from time cards. The Project Management application can also calculate the costs of affected CIs in a
  project. The Project Management Costing add-on is required to track costs.

* What goals do you want the project to achieve? Every project has at least one goal.
  Project goals are saved in the Goal table and can link to any task. In a typical
  scenario, link one goal to each project and keep the State field
  of the goal up to date.

{#basics-project-management__ul_bsk_g2b_5w} Create the project  
Create the project in the Project Management application after:

* Choosing an approach
* Gathering initial estimates for the planned start date
* Estimating cost
* Formulating a well-defined business case
{#basics-project-management__ul_e1l_lgt_sx}
Add project tasks, dependencies, and relationships  
After creating a project record, create tasks.

* For top-down planning, create a task that you already know includes several child tasks. Then create the child tasks and specify that they are child tasks of the first task you created.
* For bottom-up planning, create tasks for the smallest units of work first. Then you can create intermediary parent tasks that cover a group of related child tasks. For example, if there are five sequential tasks that comprise a phase of a project called install database, create the five tasks first. Then create another task called Database installation and make it the parent task of the five tasks. Rollup calculations, such as Planned duration, for the Database installation task are automatically calculated based on the child tasks.
{#basics-project-management__ul_hm1_xfb_5w}  
It is easiest to build task relationships and dependencies while creating sets of tasks.

* A dependency means that a task relies on other tasks to be performed (completely or partially) before it can be performed. For information on different types of dependencies supported, see [Project task
  relationships and dependencies](https://servicenow-prod.fluidtopics.net/19ZkzZ1W90OCBNOQbAt65g "The Project Management application enables you a create parent-child relationships between tasks and dependencies, such as finish-to-start and finish-to-finish, between tasks.").
* A relationship means a parent-child relationship whereby several subtasks are configured under a parent task or phase, which rolls up fields like Planned duration and Estimated cost.

  Use the [Gantt chart](https://servicenow-prod.fluidtopics.net/ZaLgmv7CGYjUztoIf20liQ "A Gantt chart on the planning console is a visual representation of a project timeline that shows start and end dates of tasks, and the dependencies between tasks.") with task forms and related
  lists to [build relationships](https://servicenow-prod.fluidtopics.net/19ZkzZ1W90OCBNOQbAt65g "The Project Management application enables you a create parent-child relationships between tasks and dependencies, such as finish-to-start and finish-to-finish, between tasks."). Add milestones based on the major events of a project
  and create dependencies between milestones and tasks, if necessary.

  Also set up
  notifications to alert project task assignees when their tasks move to the
  Work in Progress state. See Creating Project Tasks for more
  information on creating tasks.
{#basics-project-management__ul_iml_dgb_5w}
Assign resources or assignment groups to the tasks

User resources are the individuals in an organization who are assigned to project tasks.
You can manage your resources with resource plans in the Resource Management
application.
Add the project to a portfolio

A portfolio is a group of related projects. If the project is related to other projects,
create a portfolio and add the project. The Project Management application provides a
useful portfolio view that makes it easy to report on the status of all projects in a
portfolio. Portfolios also include demands.

## Manage the Project

After the preceding steps are complete, the project
can be started. To measure the project against initial estimates, create a baseline, which
is a snapshot of the entire project including all planned dates for all project tasks and
milestones. The project manager can manage a project from the project
workbench.
Start the Project

[Start the project](https://servicenow-prod.fluidtopics.net/Jnns1pjYZTlFBIFRrEkXOA "Starting a project is the next step after setting up the project, populating it with tasks, and assigning resources.") by
changing the project state to Work in Progress. When you change the
State field on the Project form to Work in Progress, the Actual start date of the project changes to the planned start
date.
Monitor the Project and Customize Dashboards

You can update important project status information, such as the number of milestones
slipped. You can also view summaries for cost, scope, project risk, and so on. Modify this
information as needed with the Portfolio View related list on the
Portfolio form and display this information on the Project Overview
homepage. In addition, use the project reports installed with the application, such as
Active projects or Projects (by priority),
to show important project information.

When the project is underway, continue to
access project records and edit several items, including costs, priority, schedule, and
planned values that are not rollups. Keep detailed project records for risks and issues and
refer to them after a project is complete. Also create baselines along the way to easily see
if any project phases or tasks are slipping at the time you create the
baseline.

## Close the Project

When the project is complete, change its state to Closed complete on
the project form. When a project is in the [closed state](https://servicenow-prod.fluidtopics.net/KCW0VAHfiKg2a8FlwsvXDA "Closing the project involves more than just changing the project state to closed."), the Project Management application calculates actual values like Actual duration.

Post-project activities include analyzing project baselines and actual values and
generating a final project dashboard. You can [cancel the future resource plans](https://servicenow-prod.fluidtopics.net/ZHlYmSzqu7keUbvqgWR72w "If a project or a project task is marked Closed, the project manager can cancel the associated future resource plans. Similarly, the demand manager can cancel the future resource plans for a Closed or Deferred demand.") and [complete the allocated resource plans](https://servicenow-prod.fluidtopics.net/dzo9haIkeP29ttEu1UhAKw "If a project or a project task is marked Closed, the project manager can complete the associated Allocated resource plans. Similarly, the demand manager can complete the resource plans for a Closed or Deferred demand.") for the closed project.

If the project was successful and can be used as a template for future projects, make a
copy of it. If the project was created from a change, incident, or problem record, there are
several other activities to perform in ServiceNow.