# Move a resource assignment in Project Workspace

# Move a resource assignment in Project Workspace {#ariaid-title1}

* Release version: Xanadu
* 
* Updated July 1, 2025
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 1 minute to read

Move the resource assignment to a new start and end dates to accommodate changes in task scheduling or resource allocation. Shift assignments to balance workloads across resources and avoid over-allocation.

## Before you begin

Role required: resource_user, resource_manager

## About this task

* When you move an assignment to a new start and end dates, the initial requested or approved efforts are retained for the latest duration.
* When an assignment is moved, the Ready for review state is retained and the assignment remains accessible to resource managers for work allocation.
* You cannot move a resource assignment if actuals efforts are entered for the work.
* New assignment dates should be within the task duration dates.
{#move-resource-assignments-project-workspace__ul_rdy_rxb_wfc}

## Procedure

1. Navigate to WorkspacesProject Workspace and open a project.
2. View the resource assignment pane by enabling the Resource assignments toggle button.  
   Note:  
   If the property sn_pw.enable_resource_planning is set to true, then the Resource plan toggle button and resource assignment pane are displayed in Project Workspace. The default value is false. You must have the pps_admin role to enable this property.
3. Select a project task to view the assignments associated to the task.
4. From the resource assignment pane, select the row context menu (![Row context menu.]()) and then select Move.
5. From Move assignment modal, select a New start date using the date picker modal.
6. **Optional:** Change the assignment status using the New status list to one of the following available statuses.  
   Changing the status is restricted to the resource_manager role.
7. Select Confirm.  
   When you move the resource assignment for a group, the assignments are moved for all members of that group. You cannot move assignments for individual users within the group or for child resource assignments.
**Related tasks**   

* [Extend a resource assignment](https://servicenow-prod.fluidtopics.net/kSfyfqO2w0FVJ~8PZBL39Q "Extend the date of an allocated resource assignment and allocate resources for the extended period.")
* [Update a resource assignment from Project Workspace](https://servicenow-prod.fluidtopics.net/0cVRYxE_gAkVFSmVVp_WWQ "Update a resource assignment that is associated with a project or project task.")
* [Delete a resource assignment from Project Workspace](https://servicenow-prod.fluidtopics.net/RKd9gZlGIFKrNoTcIph8GA "Delete a resource assignment from Project Workspace. Deleting an assignment also deletes all associated resource allocations.")
* [Update the resource allocation in a heatmap](https://servicenow-prod.fluidtopics.net/4VRpaP7Z1C19v3fUYF19Vg "Use the allocation heatmap capability in Project Workspace to view and update the resource allocation.")
* [Realign resource assignment to project task](https://servicenow-prod.fluidtopics.net/_Y3BsvblTYIFwo0j8J19RA "Realign or synchronize the resource assignment dates with the project task dates. This synchronization helps to schedule and align the resource assignments with the timeline of project task.")