# Create a project cost plan

# Create a project cost plan {#ariaid-title1}

* Release version: Xanadu
* 
* Updated August 1, 2024
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 3 minutes to read

Project cost plans capture the costs of projects. Create a cost plan to specify the
unit cost of a cost type for a fiscal period.

## Before you begin

Role required: it_project_manager

Application required: Project Portfolio Management
with Financials

## About this task

The application automatically creates [cost plan breakdown
records](https://servicenow-prod.fluidtopics.net/w9UEayp5MlTwkUR4n12cRw#cost-plan-breakdown "A cost plan breakdown captures the estimated cost and actual cost for every fiscal period. Cost plan, project, demand, program, and portfolio are the breakdowns types that are available.") when you save the cost plan. Cost plans can also have associated [expense lines](https://servicenow-prod.fluidtopics.net/u2GKnz2JBWQ~IUJ4etmhPA "A project expense line is cost associated with a specific source, such as a user, fixed asset, or a CI. Expense lines are part of project cost plans.").  
Note:  
Cost plans are automatically created for resource plans that are associated to projects and project tasks.To use multiple currencies, create a new cost plan for another currency.

## Procedure

1. Open the project form.
2. In the related links, click Cost Plans.
3. Click New.  
   Note:  
   To create a cost plan from the Financials tab in Project Workspace, click Manage.
4. On the form, fill in the fields.  
   {#t_CreateAProjectCostPlan__table_mb3_rfw_1r__entry__2}

   | Field | Description |
   |-|-|
   | Name | Descriptive name of the cost plan. |
   | Project/Demand | Project or demand to which the cost plan belongs. |
   | Start fiscal period | Indicates the starting fiscal period. When you change the start fiscal period, the associated cost plan breakdowns also change. Start fiscal period also changes when you create cost plan breakdowns earlier than the start fiscal period. |
   | End fiscal period | Indicates the ending fiscal period. When you change the end fiscal period, the associated cost plan breakdowns also change. End fiscal period also changes when you create cost plan breakdowns later than the end fiscal period. |
   [Table 1. Cost Plan form]

   {#t_CreateAProjectCostPlan__table_mb3_rfw_1r} {#t_CreateAProjectCostPlan__table_uq5_1pz_fdc__entry__2}

   | Field | Description |
   |-|-|
   | Entered currency | Currency in which you want the cost plan to be created. If the selected currency is different from the functional currency, the corresponding [budget reference rate](https://servicenow-prod.fluidtopics.net/_Ai6WHkxB7MrOQ7KOO1MyA "The support for use of multiple currencies provides conversions for budget items in different currencies.") is used to calculate the total planned cost, planned capital, planned operating of the project. |
   | Unit cost | Cost of a single unit of the resource, which is in terms of entered currency. |
   | Quantity | Quantity of the resource that is required. |
   | Recurring | Option to indicate that the cost is recurring for each fiscal period. Quantity x Unit cost incurred for every fiscal period. |
   | Cost type | [Cost type definition](https://servicenow-prod.fluidtopics.net/QIrrP1yYKHaCfSNqJ_Mhtw "Create a cost type definition to associate a cost type, operating, or capital, to an account in the General Ledger from the Financial Management application. Create a cost type definition if you are using Project Portfolio Management with Financials."). |
   | Investment | Name of the investment created for the project. This field appears only if the legacy Investment Funding (com.snc.investment_funding) plugin is activated or the Investment Funding (sn_invst_pln) application is installed. |
   | Source type | Funding entity to associated with the project investment for funding. This field appears only if the legacy Investment Funding (com.snc.investment_funding) plugin is activated or the Investment Funding (sn_invst_pln) application is installed. |
   | Source | Funding entity value from which you request fund. The field is available when you select a value in the Source type field. This field appears only if the legacy Investment Funding (com.snc.investment_funding) plugin is activated or the Investment Funding (sn_invst_pln) application is installed. |
   | Total planned cost | Total estimated cost of the cost plan. If the cost is recurring, the calculation is Quantity x Unit cost x number of fiscal periods. If the cost is non-recurring, the calculation is Quantity x Unit cost. |
   | Functional currency | Currency that is obtained from the [glide.system.locale property](https://www.servicenow.com/docs/access?context=currency-properties&version=xanadu&pubname=xanadu-platform-administration&ft:locale=en-US). For upgraded customers, if the selected currency is different from the functional currency configured in the Financial Management application, the corresponding [budget reference rate](https://servicenow-prod.fluidtopics.net/_Ai6WHkxB7MrOQ7KOO1MyA "The support for use of multiple currencies provides conversions for budget items in different currencies.") is used to calculate the total planned cost, planned capital, planned operating of the project. Note: If budget reference rates are not defined, then exchange rate is considered as 1. For example, if functional currency is USD, entered cost is EUR, and no exchange rate is defined, then 1000 USD equals to 1000 EUR. |
   | Cost in functional currency | Value that is rolled up from the Functional cost field of all cost plan breakdowns. |
   | Total actual cost | Value that is rolled up from the Actual cost field of all cost plan breakdowns. |
   | Estimate at Completion | Sum of all actuals for past fiscal periods added to the functional cost for future fiscal periods. For example, the duration of a project is from January 01 to December 31, and if you check the Estimate at Completion in the month of May, it is calculated as: `Sum of actuals from Jan to April + Sum of functional cost from May to December`. |
   [Table 2. Financials section of the Cost Plan form]

   {#t_CreateAProjectCostPlan__table_uq5_1pz_fdc}  
   Note:  
   When you change the planned start date of a project, the associated cost plans and resource plan also change. The [project property](https://servicenow-prod.fluidtopics.net/MltM0fRsOZDAiOF6la~BfQ#r_InstalledWithProjectManagement__project_application_properties) Change Resource Plan and Cost Plan Start Date with Demand or Project Start Date Change controls the behavior for project start date change.
5. Click Submit.
{#t_CreateAProjectCostPlan__steps_wk3_flv_k1b}

## What to do next

To recalculate the values in the Estimate at Completion field,
use the Calculate Estimate at Completion related link. To
view the cost plan breakdowns, click the Cost Plan Breakdowns
related list.
* **[Cost plan breakdown](https://servicenow-prod.fluidtopics.net/w9UEayp5MlTwkUR4n12cRw#cost-plan-breakdown)**   
  A cost plan breakdown captures the estimated cost and actual cost for every fiscal period. Cost plan, project, demand, program, and portfolio are the breakdowns types that are available.
* **[System-generated cost plans](https://servicenow-prod.fluidtopics.net/I4j9NfZGtfnXrBddUlU2ww)**   
  When an expense line is created without populating the Cost Plan field, system-generated cost plans are created automatically.

**Related concepts**   

* [Create and manage waterfall projects](https://servicenow-prod.fluidtopics.net/qYAtAhluJwRjZIVT7aE63g "An overview of the tasks involved in creating a waterfall project.")
* [Project and portfolio funding](https://servicenow-prod.fluidtopics.net/yo_huy9HdxJmO3rWIAQX6A "Specify the amount of money that projects and portfolios are allowed to have.")
* [RIDAC records for a project in Project Workspace](https://servicenow-prod.fluidtopics.net/h_7YaQ7eDOfvXq3oeGNQnQ "RIDAC is an acronym for Risk, Issue, Decision, Action, and Request Change records. In Project Workspace, you can create a risk record for your project that you can convert to other records during the project life cycle. You can track issues and avoid copying relevant details in the related records.")  
**Related tasks**   

* [Copy a project](https://servicenow-prod.fluidtopics.net/R7uzpvuqVrOxm6jJDhABmA "Another option for creating a project is to copy an existing project with all its tasks and relationships. After you specify the start date for the copy, the system adjusts all task start and end dates automatically.")
* [Create baseline of a project](https://servicenow-prod.fluidtopics.net/rpnMdmmWB4r_uM8689QhCQ "Create a schedule baseline and financial baseline of a project. A schedule baseline captures planned dates of all tasks and milestones at a particular moment in time. A financial baseline captures benefit and financial metric information (snapshot of cost plan, benefit plan, and project-level financial metrics) at a particular moment in time.")
* [Assign a project schedule](https://servicenow-prod.fluidtopics.net/uQb8CgchFUzq8J5Q4yM1bA "Without an assigned schedule, a project calculates a day as a full 24 work hours. To schedule tasks by a more realistic work day, assign a schedule to the project. If the schedules provided in the base system do not suit your needs, define a new one.")
* [Create a monetary benefit plan for a project](https://servicenow-prod.fluidtopics.net/PRZ20AA5IgPcY0t6_VLNtA "Project benefit plans capture the potential benefits accrued by the project when the project is executed. Create a monetary benefit plan to specify the estimated benefit in a category spanning one or more fiscal periods.")
* [Create a non-monetary benefit plan for a project](https://servicenow-prod.fluidtopics.net/TZKTTgApzzzMVwrXHWah_g "Create a non-monetary benefit plan to specify the estimated benefit in a category spanning one or more fiscal periods. Project benefit plans capture the potential non-financial benefits accrued by the project when the project is executed.")
* [Associate monetary and non-monetary benefit plans](https://servicenow-prod.fluidtopics.net/4lFKAossSu8aM62u4y~6gQ "Associate monetary and non-monetary benefit plans, so that you can capture the potential benefits (financial and non-financial) accrued by the project for the hybrid benefit plans.")
* [Create an expense line](https://servicenow-prod.fluidtopics.net/u2GKnz2JBWQ~IUJ4etmhPA "A project expense line is cost associated with a specific source, such as a user, fixed asset, or a CI. Expense lines are part of project cost plans.")
* [Generate labor costs](https://servicenow-prod.fluidtopics.net/J46TUNq9Y66fMVEU8EcHIw "Generate labor costs based on the planning attributes configured for financials in the planning attributes page for the resource assignments in a project.")
* [Migrate budget of active projects to Next Experience](https://servicenow-prod.fluidtopics.net/iazR~rOxWHjUaWnw7uY_tw "Migrate the project budget to Next Experience to manage the financials using Project Workspace.")
* [Migrate financial baselines of projects to Next Experience](https://servicenow-prod.fluidtopics.net/DPaazW2jMtb3VaZYwwoslQ "Migrate the financial baselines of your project to Next Experience to manage the financial using Project Workspace.")
* [Create a project status report](https://servicenow-prod.fluidtopics.net/6uavTNJry6CKosZevPBTAA "You can periodically create project status report from the related lists of the project form. The project status report created for the most recent status date updates the status of the project in portfolios.")
* [View project status reports](https://servicenow-prod.fluidtopics.net/1EbO_5jbF6kUblFSUVoQwA "Project status reports provide the most recent, at-a-glance progress of a project displayed in several categories.")
* [Create a cost type definition](https://servicenow-prod.fluidtopics.net/QIrrP1yYKHaCfSNqJ_Mhtw "Create a cost type definition to associate a cost type, operating, or capital, to an account in the General Ledger from the Financial Management application. Create a cost type definition if you are using Project Portfolio Management with Financials.")
* [Allocate budget to a project](https://servicenow-prod.fluidtopics.net/iCor4zzDMQKgy9hZOkmU6Q "Set the budget of a project according to the fiscal years.")