# Create a dependency from the planning console

# Create a dependency from the planning console {#ariaid-title1}

* Release version: Xanadu
* 
* Updated August 1, 2024
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 1 minute to read

You can create a dependency between two tasks on the planning console.

## Before you begin

Role required: it_project_manager

## About this task

You can create any type of dependency. See [Project task relationships and dependencies](https://servicenow-prod.fluidtopics.net/19ZkzZ1W90OCBNOQbAt65g "The Project Management application enables you a create parent-child relationships between tasks and dependencies, such as finish-to-start and finish-to-finish, between tasks.") for an
explanation of each type.

You can also create dependencies by using the Predecessor column on the Planning
Console. See [Predecessor dependencies in the planning console](https://servicenow-prod.fluidtopics.net/p2XtGZIvT2fgZGxVkWQjPw "In the WBS section of the planning console, you can create dependencies between tasks by specifying a series of values.") for more
information.

## Procedure

1. Click a task on the Gantt chart portion of the planning console.  
   A white circle appears on either end of the task, one at the start of the task and the other at the end of the task.
2. To create a dependency, click one of the white circles and drag it to the start or end of another task.
3. Double-click the dependency line to see the dependency on the Planned Task Relationship form.
4. Confirm that your dependency is correct.  
   You can [make changes to the dependency](https://servicenow-prod.fluidtopics.net/_TFE1hwA0ShfyDFx27nUdA "You can modify a dependency when editing the tasks that are linked in the dependency, the dependency type, or the lag time.") as needed.